IDC completes two Drilling Projects in Iraq

By John Lee.

The Iraqi Drilling Company (IDC) has recently completed the drilling of oil well 48 at the Nasiriyah oil field.

The company’s general manager, Engineer Basem Abdel Karim Nasser, said this was part of the contract with Dhi Qar Oil Company (DQOC) to drill 20 oil wells at the field in cooperation with US-based Weatherford.

Drilling operations were carried out over 18 months using the IDC 44 drilling rig.

IDC has also recently completed the drilling of oil well J120P in the Al-Gharraf field, which reached a depth of 3,037 meters.

Nasser said this was the thirteenth well drilled as part of the contract with the Malaysian Petronas company to drill 28 directional oil wells in the Al-Gharraf oil field in Dhi Qar Governorate.

The work was carried out using the IDC 54 drilling rig (pictured), which has a power of 2000 HP.

The company owns 43 drilling and reclamation rigs distributed in the Iraqi oil fields.

(Source: Ministry of Oil)

The post IDC completes two Drilling Projects in Iraq first appeared on Iraq Business News.

China Wins Engineering Deal for Giant Iraqi Gas Plant

By John Lee.

China Petroleum Engineering Procurement & Construction (CPECC) has reportedly won an engineering contract for a plant to process gas from the Gharraf (Garraf) and Nasiriyah fields.

According to Upstream Online, the contract was awarded by lead contractor Baker Hughes.

More here (subscription required)

(Source: Upstream Online)

The post China Wins Engineering Deal for Giant Iraqi Gas Plant first appeared on Iraq Business News.

IDC starts Drilling 20 Oil Wells at Nasiriyah

By John Lee.

The Iraqi Drilling Company (IDC) has started work on the first of its 20 oil wells at the Nasiriyah oil field in Dhi Qar.

IDC’s Director General, Basem Abdul Karim, said that the project is part of a contract with the Dhi Qar Oil Company (DQOC) in cooperation with Weatherford.

The planned depth of the well is 2,200 meters.

The project is to be completed within 18 months.

(Source: Ministry of Oil)

The post IDC starts Drilling 20 Oil Wells at Nasiriyah first appeared on Iraq Business News.

Nassiriyah Hospital Fire: Arrest Warrants Issued

By John Lee.

Authorities in Iraq are facing accusations of negligence following the fire at the al-Hussein coronavirus hospital in Nassiriyah on Monday.

Estimates of the death toll range from 60 to over 100, with more than 100 people injured.

The fire is believed to have started when sparks from faulty wiring caused an oxygen tank to explode.

Arrest warrants have been issued for several officials.

(Sources: Reuters, BBC, The New Arab)

The post Nassiriyah Hospital Fire: Arrest Warrants Issued first appeared on Iraq Business News.

New Contracts for Iraqi Drilling Company (IDC)

By John Lee.

The Iraqi Drilling Company (IDC) has announced its intention to conclude contracts with Chinese and American companies operating in Iraq to drill and rehabilitate dozens of oil wells in the country.

The company indicated it is about to start drilling 20 wells in the Nasiriyah field in Dhi Qar, which are included in a long-term plan with the Dhi Qar Oil Company (DQOC) to advance the oil sector, due to be completed in over two years.

After the relative relaxation of the impacts of the coronavirus, the Iraqi Drilling Company resumed its negotiations with the international companies developing oil fields in the country and their counterparts affiliated with the Ministry of Oil in the provinces, in preparation for signing the postponed contracts with the aim of enhancing Iraq’s energy capabilities.

The drilling and rehabilitation contracts, hoped to be concluded soon, include drilling 37 wells in the Zubair field for the Italian company ENI, the main operator of the field, and starting discussions with BP, the main contractor in the Rumaila field, to develop the giant field west of Basra.

This is in addition to the near signing of a contract to drill 43 wells in Majnoon field with the Basra Oil Company (BOC), which is the third largest oil field in the world, with reserves of 6.12 billion barrels.

The Iraqi Drilling Company has completed all its preparations to sign a contract with the Central Oil Company, to drill 27 wells in the East Baghdad field, and it continues its discussions with the Maysan [Missan] Oil Company (MOC) to sign a contract for drilling 22 wells in the Bazargan field as well as rehabilitating another 150 wells and a contract to operate a number of drilling towers and rehabilitation of a large number of wells in the Kirkuk fields with the North Oil Company (NOC).

(Source: Govt of Iraq)

The post New Contracts for Iraqi Drilling Company (IDC) first appeared on Iraq Business News.

Amarinth delivers $650k Pumps to Garraf Oilfield

UK-based pump company Amarinth has delivered four API 610 VS4 vertical pumps with Plan 53B seal support systems for the Oil Train 5 Project at Garraf oilfield.

Located at the northwest of Al-Refaei, approximately 85 kilometers north of the City of Nasiriya, half way between the Tigris and Euphrates rivers in the southeast of Iraq, Garraf is the fifth largest oil and gas field in Iraq with estimated reserves of 1 million barrels of oil.

Petronas and its partners are currently increasing production in the field, and the addition of Oil Train 5 is expected to bring this up to 230,000 barrels per day.

The $650,000 order of four API 610 VS4 vertical pumps with Plan 53B seal support systems was placed with Amarinth by China Petroleum Engineering Procurement & Construction (CPECC).

According to a press release from the company, this was the first time that CPECC had ordered from Amarinth and the decision was made based on Amarinth’s proven ability to design and deliver bespoke API 610 pumps for hazardous areas, along with the company’s previous experience of successfully supplying pumps for the Iraq market, all to strict deadlines.

The pumps were manufactured in Inconel Alloy 625, a nickel-based superalloy that possesses high strength properties, resistance to elevated temperatures and excellent protection against corrosion and oxidation. In addition, the Plan 53B seal support systems required a bespoke mounting configuration and piping design.

Amarinth successfully completed the design, manufacture, and delivery within the required 34 weeks.

Oliver Brigginshaw, Managing Director of Amarinth, commented:

“We are delighted with this first order from CPECC, again underlining our strength in the Middle East, and in particular our ability to delivery API 610 pumps into the developing oil and gas projects in Iraq.”

(Source: Amarinth)

The post Amarinth delivers 0k Pumps to Garraf Oilfield first appeared on Iraq Business News.

Cabinet commits resources to Dhi Qar province

The Iraqi Cabinet held an extraordinary meeting in the city Nasiriyah in Dhi Qar province on Monday under the chairmanship of Prime Minister Mustafa Al-Kadhimi.

At the start of the meeting, the Prime Minister said that the people of Dhi Qar had sacrificed much for Iraq, but they have suffered from the consequences of past marginalisation. He affirmed that this government is determined to address the challenges facing the province.

Following discussions, the Cabinet approved several measures to improve services and boost investment in Dhi Qar, including:

  • Establish Dhi Qar Reconstruction Council to oversee the implementation of key projects in the province
  • Establish a working group to review all delayed and incomplete projects in Dhi Qar to ensure that work on these projects is resumed, giving a priority to projects that have direct impact on the lives of citizens. The working group will be chaired by the Secretary-General of the Council of Ministers, with the membership of the Governor of Dhi Qar, the Deputy Minister of Planning, the Deputy Minister of Construction, Housing and Municipalities, and representatives from the Ministries of Finance, Electricity, Oil and Education
  • Grant the Governor of Dhi Qar the necessary powers to oversee the construction of new roads, rehabilitation of water purification plants, and the rehabilitation and maintenance of hospitals and health centres
  • Direct the Ministry of Oil to allocate 500 million dinars annually to the Heart Centre in Dhi Qar and to the local Health Department
  • Direct the Ministry of Communications to allocate 10 billion dinars to Dhi Qar
  • Direct the Ministry of Health to provide hospitals in the province with medical equipment and supplies
  • Direct the Ministry of Education and Scientific Research to follow up on the progress of Al-Shatra University Project which was established in 2013
  • Direct the Agricultural Bank, the Housing Fund and the Industrial Bank to simplify the procedures for granting loans to the people of Dhi Qar because of the exceptional circumstances facing the province
  • Expedite the completion of Dhi Qar Industrial City and Dhi Qar Refinery
  • Expedite the construction of school buildings and hospitals with a high completion rate

The Cabinet also approved several technical and administrative measures related to Dhi Qar aimed at delivering tangible and rapid improvement across a number of key public services.

(Source: Govt of Iraq)

The post Cabinet commits resources to Dhi Qar province first appeared on Iraq Business News.

Cabinet to Support Projects in Health, Oil sectors

The Iraqi Cabinet held its regular weekly meeting in Baghdad on Tuesday under the chairmanship of Prime Minister Adil Abd Al-Mahdi.

The Prime Minister told the Cabinet that the current government will continue to discharge its  duties until the formation of the next Iraqi government.

The Prime Minister then outlined some of the key achievements of this government which will be detailed in a comprehensive report to be published soon.

The Cabinet discussed several policies and approved administrative measures to support projects in the health sector, including building general hospitals in Iraqi provinces with a capacity of 400 beds each.

The Cabinet approved recommendations submitted by the Ministerial Council for Energy to allow Dhi Qar Oil Company (DQOC) to borrow 265,000,000 US dollars from the Trade Bank of Iraq (TBI) for the purpose of implementing a project to expand the production at Al-Nasiriyah oil field by an additional 100,000 barrels per day.

(Source: Govt of Iraq)

Iraq to Build 5 New Refineries

By John Lee.

The Iraqi Ministry of Oil has reportedly announced that it will select a number of international investment companies to build five new refineries around the country:

  1. Kirkuk with a capacity of 70,000 barrels per day (bpd);
  2. Wasit capacity of 140,000 bpd;
  3. Nasiriyah capacity of 140,000 bpd;
  4. Basra card 140,000 bpd; and
  5. al-Faw capacity of 300,000 bpd.

According to Asharq Al-Awsat, the Ministry is financing Karbala refinery which is about 78 percent completed, and once it is fully constructed, it will provide about 9 million liters per day of high-quality gasoline, in addition to various oil derivatives in accordance with international standards.

(Source: Asharq Al-Awsat)

(Pictured: Baiji Oil Refinery)