Gazprom Neft Halves Badra Production Target

By John Lee.

Russia’s Gazprom Neft has reportedly revised down its output plateau for the Badra oil field.

Denis Sugaipov, head of Gazprom Neft’s department of large projects, told Reuters that the consortium running the project has proposed setting the output plateau for the next few years at its current level of around 85,000 bpd, as the field is more geologically complex than previously thought.

This is half the level initially planned as a plateau to be reached in 2017.

The field is being developed by Gazprom (30%), KOGAS (22.5%), Petronas (15%), TPAO (7.5%), Iraqi state-owned Oil Exploration Company (25%).

According to Reuters, $4.0 billion has been invested in the plant so far, including $1 billion for a gas processing plant; another $2.5 billion is planned to be invested by 2030.

(Source: Reuters)

Gazprom Neft commissions New Gas Plant at Badra

Russia’s Gazprom Neft has launched the commercial operation of a 1.6 billion cubic metres capacity gas processing plant at its Badra field, Iraq.

Alexander Novak, Minister of Energy of the Russian Federation, was present at the opening ceremony for the new facility, together with the Minister of Oil of the Republic of Iraq, Jabbar al-Luaibi, and Gazprom Neft CEO Alexander Dyukov.

Dry feed gas, processed at the Badra field, is transported via a 100-kilometre pipeline to the Az-Zubaidiya power station, supplying electric power not just to provinces throughout Iraq, but also to the capital city of Bagdad.

In addition to this, gas will be used to meet the Badra project’s own needs as fuel for the gas-turbine power plant. Five gas turbines are able to produce a total 123.5 MW of electric power, supplying oil and gas processing facilities, drilling rigs and oil-producing wells. A 10-MW overhead power line will soon begin feeding into the Gazprom Neft Badra accommodation complex, as well as into the town of Badra and neighbouring population centres.

Natural gas liquids (NGLs) produced at the Badra project’s gas processing plant will be used to produce LPG to be supplied to the Iraqi state-owned Gas Filling Company. The plant also includes facilities for sulphur production and granulation.

Alexander Dyukov, Gazprom Neft CEO, made the following comment at the official opening ceremony of the gas plant:

Gazprom Neft is continuing its development of the Badra field, in strict adherence to the field development plan. Today sees the full-cycle gas plant — built by our company using the most cutting-edge technologies available on the world market — going into commercial production.

“This is a unique enterprise for the region, at which Gazprom Neft has, since starting work, been able to monetize all of the hydrocarbons produced here, ensuring associated-petroleum-gas (APG) utilisation of at least 95 percent.

(Source: Gazprom Neft)

Gazprom Neft not to Cut Production at Badra

By John Lee.

Russia’s Gazprom Neft has said it expects production at the Badra oilfield to stay between 85,000 and 90,000 barrels per day (bpd) in 2018.

Deputy chief executive Vadim Yakovlev (pictured) told Reuters that Baghdad has not asked the company to curtail production, despite reports that the Oil Ministry had asked foreign producers to cut investment to reduce the cash-strapped government’s contribution in shared ventures.

Yakovlev added that production at Badra is expected to plateau as high as 110,000 bpd in the future.

(Source: Reuters)

Petrofac in Kurdistan Deal with Gazprom Neft

Petrofac has secured a three-year master services agreement (MSA) to support Gazprom Neft Middle East B.V. with the provision of engineering services on a call-off basis for the Garmian field in the Kurdistan region of Iraq.

The MSA was secured following a competitive tendering process and augments Petrofac’s extensive footprint in Iraq, where it has been providing engineering, operations, maintenance and training services since 2010.

Gazprom Neft has been Operator of the Garmian field since early 2016. Through the provision of engineering services Petrofac aims to support the planned brownfield works to debottleneck and expand the Central Processing Facility (CPF).

Steve Webber, Senior Vice President, Petrofac Engineering & Production Services, East said:

We are delighted Gazprom Neft has selected Petrofac as one of its key suppliers in support of the Garmian field CPF upgrade project.

“We have been working with this key client in Iraq for more than three years and hope to take this opportunity to build on our relationship through the demonstration of Petrofac’s fit-for-purpose and value-driven engineering solutions in the Kurdistan region.

(Source: Petrofac)

Gazprom’s Largest Ever Maritime Shipment – from Badra

Gazprom Neft Badra, operator of the Badra field, has undertaken the largest ever maritime shipment of oil for export in the company’s history, with 1.78 million barrels of hydrocarbons being despatched for the United States in the New Solution crude oil tanker.

This is, to date, the second oil consignment to the American market by Gazprom Neft Badra — recipients of the preceding 12 shipments having been European companies and refining facilities in the Asia—Pacific region.

Hydrocarbon exports from Iraq by Gazprom Neft are delivered by the State Oil Marketing Company (SOMO) and comprise the cost-recovery component of Gazprom Neft’s development of Badra field.

(Source: Gazprom Neft)