Aggreko completes Flare-Gas-to-Power plant in KRI

UK-based Aggreko has announced that it has completed commissioning of the largest flare-gas-to-power project in the Middle East to date at 165 MW capacity.

The plant is situated nearby the Saqala [Sarqala] Field, Garmain block, South East Kurdistan.

The 165 MW modular power plant has run at full capacity for 72 hours in the project’s final site acceptance test (SAT), marking successful on-time, on-budget delivery.

The plant is run on approximately 40 million square cubic feet (SCF) per day of associated petroleum gas (APG) from the Saqala Field, saving 840 tonnes of CO2 per day, and cutting flaring by a third.

Delivered over the course of 2020-2021 against the backdrop of the pandemic, the project was conceived and executed in close collaboration with Kurdistan’s Ministry of National Resources (MNR) and Ministry of Electricity (MOE).

Aggreko also delivered a new 6km gathering pipeline to transport the APG to the power plant, and upgraded 7km of 33 kV and 33km of 132 kV overhead cables to new high tensile low sage (HTLS) conductors in order for the local distribution grid to handle the new power plant’s full output.

Ahmed Mufti, Kurdistan Regional Government’s Deputy Minister of Natural Resources (MNR) said:

“We worked with Aggreko to provide a creative solution to convert flare gas to power in a way that directly benefits the local population and the regional in general, while creating a positive environmental impact and improving air quality.”

Phil Burns, Managing Director for Aggreko Middle East, comments:

“Kurdistan’s Regional Government has been forward-thinking in looking for ways to capture and convert gas that would otherwise be flared, to unlock production and power the local economy. We are extremely proud to have worked with the Ministries to deliver the Middle East’s largest flare gas to power project to date, while upgrading the local infrastructure to the lasting benefit of the community and businesses it serves.”

The project is now contracted to run for four years, delivering power 24/7/365.

Built using 192 MW of modular gas generators, the plant can easily be scaled up or down in response to changing gas volumes.

Approximately 60 Aggreko engineers have delivered the project, with 80 local jobs created directly and indirectly for the site’s delivery and ongoing operation, including 44 local nationals who have already commenced Aggreko’s official training scheme.

More here.

(Source: Aggreko)

The post Aggreko completes Flare-Gas-to-Power plant in KRI first appeared on Iraq Business News.

Gazprom Neft developing Fourth Well at Sarqala

By John Lee.

Russia’s Gazprom Neft has produced its four-millionth tonne (32-millionth barrel) of oil since starting commercial development of the Sarqala field in the Kurdistan Region of Iraq (KRI).

Three wells are now in operation at this field, with daily production running at about 3,100 tonnes (24,000 barrels) per day.

Limitations arising under the COVID-19 pandemic notwithstanding, Gazprom Neft Middle East B.V. is continuing to develop this field and is implementing a number of key production projects, including drilling a fourth well, the commissioning of which will increase production to 4,100 (around 32,000 barrels) per day. The commissioning of this well is scheduled for the first half of 2021.

Gazprom Neft Middle East B.V. is involved in this project with the Government of the KRI as part of the latter’s development of the region’s energy supply system. Associated petroleum gas (APG) produced at the Sarqala field will be used as fuel for energy facilities currently under development by government authorities.

This programme envisages the construction of a 4.5-kilometre gas pipeline to connect the field to power generation facilities. Implementing this project will not only increase APG utilisation at the field, but will also facilitate energy supplies to several districts within the KRI.

(Source: Gazprom Neft)

The post Gazprom Neft developing Fourth Well at Sarqala first appeared on Iraq Business News.

Gazprom “Not Reducing Investment” in Iraqi Kurdistan

By John Lee.

Russia’s Gazprom Neft has reportedly said it will not reduce investment in its projects in Iraqi Kurdistan, despite a request from the Kurdistan Regional Government (KRG) to do so.

Reuters reports that following a slump in oil prices, oil producers have been asked to reduce their investments, which governments often have to partially reimburse as part of their contractual arrangements.

Gazprom Neft holds a participating interest of 40 percent in the Garmian block and 80 percent in the Halabja and Shakal blocks. The Sarqala field is located within the Garmian block.

More here.

(Source: Ekurd, Reuters)

Gazprom Neft expands Oil Production at Sarqala

Russia’s Gazprom Neft has commissioned a third production well at its Sarqala field in the Kurdistan Region of Iraq (KRI)

Potential production at this new well is estimated at 12,000 barrels per day. Cumulative daily oil production at the field following the commissioning of the Sarqala-3 well has increased by 25 percent reaching 35,000 barrels.

The well runs to a total depth of 3,291 metres, with drilling having been undertaken under the challenging geological conditions of the Sarqala field — anomalously high pressure and reservoir temperature having demanded the use of a selection of 11 technological solutions. The construction of the Sarqala-3 well has, as a result, involved the use of large-diameter casing pipes with ultra-strong thread connections, weighted drilling mud for bottom-hole flushing, and cement incorporating mineral-based and iron-oxide additives.

Drilling the well has involved an international team, with members from 20 countries. The project was implemented by Gazprom Neft Middle East, with technical support from the Gazprom Neft Science and Technology Centre.

Vadim Yakovlev, First Deputy CEO, Gazprom Neft, commented:

“The Middle East remains an area of strategic interest to Gazprom Neft, being a region with a rich resource base, and a demonstrable willingness to allow access to investors. Experience in implementing projects from scratch — both in exploration and production — is important to us. We are continuing to evaluate opportunities for the further development of our business in the Middle East — independently and in partnership with other companies — both using the synergies offered by existing project infrastructure, as well as at other assets.”

(Source: Gazprom Neft)

Gazprom Neft commissions Second Well at Sarqala

Gazprom Neft subsidiary Gazprom Neft Middle East B.V. has commissioned a second well — the Sarqala-2 — at its Sarqala field (within the Garmian block), located in the Kurdistan Region of Iraq (KRI).

The new well is currently producing 11,000 barrels per day (bpd), with potential to increase this to 15,000. Total daily production at the field has now increased more than two-fold, exceeding 21,000 bpd.

Sergei Petrov, General Director, Gazprom Neft Middle East B.V. commented:

“The Sarqala-2 well is operating under high reservoir pressure and temperature. But by using exceptional technical solutions in well construction we have been able to make significant reductions in operating costs, as well as bringing the project in on time.”

Denis Sugaipov, Director of Major Projects Upstream at Gazprom Neft, added:

“Thanks to the commissioning of this new well we have been able to confirm our geological prognoses and obtain updated information on strata composition at the Sarqala field. The geology of the KRI is, generally, under-researched, so this new well is of major importance in terms of gaining knowledge and experience of the field.”

First oil from the Garmian block was obtained in 2011, with commercial crude shipments from the field commencing as early as 2015. As at 15.04.2018 total cumulative production at the field stood at seven million barrels of oil.

The first phase of expanding gathering and treatment capacity to 25,000 bpd is now complete, with work continuing on expanding infrastructure to accommodate 35,000 bpd. Drilling of the Sarqala-3 well is planned for Q3 2018, completing Phase I of field development.

(Source: Gazprom Neft)